Answer:
Spending variance will be equal to -729
Explanation:
We have given wages and salary is $2060 per month plus $442 per birth
We have given total number of birth = 117
So standard cost = $2060+117×$442 = $53774
Actual wages and salary for the month is = $54500
We have to find the spending variance
Spending variance is given by
Spending variance = Standard cost - actual cost = $53774 - $54500 = -729
So spending variance will be equal to -729