jagrutibangale4526 jagrutibangale4526 27-05-2023 Business contestada You are a project manager working on a small marketing project to launch a new ad campaign. If earned value (EV) =350, actual cost (AC)=400, planned value (PV) =325. What is cost variance (CV)? A. 350 B. -75 C. -50 D. 400