The total hours needed for the crew to complete the job is 50 hours and the total direct labour cost is $3750
In order to calculate the total hours that it would take to complete the work, divide the total units needed to complete the construction work by the crew's production rate
Total hours it would take to complete the work = total units needed to complete the job / crew’s production rate
1250 units / 25 units/hr = 50 hours
Total direct labor cost = total skilled labor wages + total wages for the helps
Total skilled labor wages = base wages for a skilled worker per hour x total hours needed to complete the work
$50/hr x 50 hours = $2500
total wages for the helps = base wages for the helps per hour x total hours needed to complete the work
$25/hr x 50 hours = $1250
Total direct labour cost = $2500 + $1250 = $3750