A worker takes 3 hours to do a job. A new worker takes 5 hours. How long does it
take them if they work together?

Respuesta :

khushiraj29
khushiraj29 khushiraj29
  • 18-09-2020

time taken by a worker= 1/3 hours

time taken by the new worker= 1/5 hours

time taken to complete the work if they work together

= 1/3 + 1/5

= 5+3/15

=8/15

=15/8 hours

Answer Link

Otras preguntas

For each value of w, determine whether it is a solution to 6w +9=33. Is it a solution?
Match the dates to the correct spot on the timeline based on when each event occurred in history.
If you are going to compare your generation from that of the old ones, which do you think is better?​
At a construction site, a stack of bricks weighs 75 kilograms. How much does this stack of bricks weigh, in pounds?
3.0 moles of nitrogen is reacted with 11.0 moles of hydrogen to produce ammonia according to the chemical equation shown below. Which one of the following state
162:53:55 AD and MN are chords that intersect at point B. A circle is shown. Chords A D and M N intersect at point G. The length of A B is 9, the length of B D
What is the literary device here? "Some books are meant to be chewed and digested." I was thinking a pun because puns have two meanings. I thought that chewed a
GED Problem Dan can ship up to 4 pounds for $10. The contents of a package weigh 2.8 pounds. How many more pounds can Dan add to the package without paying more
what is the rate for -6
Help meeeee please Geometry