Bonita Company assigns overhead based on machine hours. The Milling Department logs 2350 machine hours and Cutting Department shows 3990 machine hours for the period. If the overhead rate is $7 per machine hour, the entry to assign overhead will show a _______.

Respuesta :

Explanation:

The computation of the overhead amount is shown below:

= (Milling department machine hours + cutting department machine hours) × overhead rate per machine hour

= (2,350 machine hours + 3,990 machine hours) × $7

= 6,340 machine hours × $7

= $44,380

So for assigning the overhead cost we have to credited the manufacturing overhead for $44,380