Answer:
Explanation:
exponential smoothing alpha = 0.5
formula = Previous demand x Alpha + previous forecast x (1 - alpha)
26 32 40 27 30
26 26 29 34.5 30.75
week 2 forecast
26x0.5 + 26x0.5 = 26.
week 3 forecast
32x0.5 + 26x0.5 = 29
use the same procedure for week 4 and week 5
week 6
30x0.5 + 30.75x0.5 = 30.375
Demand Forecast for week 6 = 30.38