Answer:
43.54
Explanation:
Effective overburden pressure will be [tex]6m\times 9.7=58.2 kN/m^{2}[/tex]
Overburden correction is given by
[tex]C_N= \sqrt{\frac {95.76}{p_o}}[/tex]
Where and are effective overburden pressure and overburden correction
Substituting the value of overburden pressure then
[tex]C_N= \sqrt{\frac {95.76}{58.2}}= 1.282716\approx 1.28[/tex]
Taking hammer efficiency of 0.8, drill rod length correction factor of 0.9 and borehole correction factor of 1.05 then corrected SPT value will be
[tex]45*1.28*0.8*0.9*1.05\approx 43.54[/tex]