The work breakdown structure can include specifications regarding size, color, weight, or performance parameters, such as speed, uptime, throughput, processing time, or operating temperature range, that the project result must satisfy?

a. True b. False

Respuesta :

Answer: the answer is false

Explanation: All the work contained within the work breakdown structure is to be identified, estimated, scheduled, and budgeted

Work breakdown team includes work to be executed by the project team to accomplish the project objectives and create the required deliverables,it also includes a visual tool for defining and tracking a project deliverable and all the small components needed to create it. breakdown structures should include about three levels of detail.