Answer:
25,000
Explanation:
Given that,
Time taken from first step to final step, cycle time = 1.25 hours
Demand for candy bars = 20,000
Throughput time = 20,000 candy bars per hour
Candies in process is work in progress:
= cycle time × Throughput time
= 1.25 hours × 20,000 candy bars per hour
= 25,000
Therefore,
25,000 candy bars are in process, on average.