Answer:
The kind of productivity measure that could be used to compute productivity is PARTIAL MEASURE
Explanation:
Partial Measure because the its does not put into consideration other inputs such as capital and energy expanded doing the job.
Mathematically, the formula for this will be;
Productivity = Output/Labour
Productivity = 400/350 = 1.14unit/hr
The formula only applied to partial measurements of productivity in terms of labour. It means that in each hour of production, the system is able to produce 1.14 unit.