One approach to identifying which activities contribute to work overload for a particular resource is to compare the resource histogram to the Gantt chart schedule, using the same timescale.
TRUE or FALSE

Respuesta :

The Given statement " One approach to identifying which activities contribute to work overload for a particular resource is to compare the resource histogram to the Gantt chart schedule, using the same timescale " is TRUE.

Explanation:

A Gantt diagram is a type of bar chart illustrating a project plan called Henry Gantt, who designed the diagram in 1910–1915, after his inventor.

Modern Gantt graphs show the relationships of dependence between activities and the current timetable.

For the planing and preparation of projects, Gantt maps are helpful. We help you decide the scope of a project, determine the needed resources, and schedule the order of activities. They are also beneficial in managing task dependencies.