The total variance is $35,000. the total materials variance is $14,000. the total labor variance is twice the total overhead variance. what is the total overhead variance? $7,000 $10,500 $14,000 $3,500

Respuesta :

$35000-$14000=$21000 (total overhead)

It said the total labor variance is twice the total overhead variance. So $21000/2=$10500

The answer is $10500. Hope this helps. If this helped, mark as branliest tq

Based on the total variance and the total material variance, we can find that the total overhead variance is $7,000.

The total variance is:

= Total material variance + Total labor variance + Total overhead variance

Assuming the total overhead variance is x, the equation becomes:

35,000 = 14,000 + 2x + x

Solving gives:

35,000 = 14,000 + 2x + x

3x = 35,000 - 14,000

3x = 21,000

x = 21,000 / 3

x = $7,000

In conclusion, the total overhead variance is $7,000