In a work breakdown structure, the sequence of tasks in which there is no slack is referred to as:

Respuesta :

Kalahira
Kalahira Kalahira
  • 25-10-2017
Critical path, the sequence of the tasks where there is no slack. Meaning if one task doesn't start on time because another has not yet been completed, there is no down time and there will inevitably be a delay in the project.
Answer Link

Otras preguntas

A mangrove swamp is more likely to exist along shores of which location?
what makes a great society in china
Suppose "35" cars start at a car race. In how many ways can the top 3 cars finish the​ race? The number of different top three finishes possible for this race o
what type of mixtures can be seperated by using fractional distillation? Give any two examples​
the expression 12xyz-45 is a a. monomial b. binomial c. trinomial d. constant
the hypotenuse of a right angle triangle is 13cm.if one other side of the triangle is 1cm shorter than the hypotenuse.calculate the third scale of the triangle​
The following information is from the December 31, 2017 balance sheet of Jackson Corporation Preferred Stock, $100 par $260,000 Paid In Capital in Excess of Pa
find the diameter of the circle whose circumference are 198cm​
What is a Joule, and what are the SI units for a Joule?
Which of the following does NOT describe a rational number? A- Non-repeating decimal B- Perfect square (ex: square root of 4) C- Terminating Decimal D- Improper