based on the information in the box, conduct mrp (material requirements planning) under lot-for-lot policy. note: please download and complete the mrp sheet attached(mrp exam template single template.xlsx download mrp exam template single template.xlsx), and upload your completed mrp sheet for your answer. each shutter consists of three slatted wood sections and two frames a firm that produces wood shutters has received two orders: one for 150 shutters (week 5) and one for 180 shutters (week 9) the wood sections are made by the firm, and fabrication takes 2 weeks the frames are ordered, and lead time is 1 week assembly of the shutters requires 1 week there is a scheduled receipt of 85 wood sections in (i.e., at the beginning of) week 1.