The project manager and team have created the schedule for the hospital wireless network
upgrade project. The schedule includes a five-day delay for the network approval before the
hospital can use the upgraded network. This causes the finish date of the project to slip by
five days. This hospital network project is:
accelerating.
forming.
lagging.
leading.