7.33 weeks
Explanation
you can easily solve this by using a rule of three
Step 1
if workers can repair 2 1/4 kilometers per week
[tex]\begin{gathered} 2\frac{1}{4}\rightarrow1\text{ w}eek \\ 2.25\rightarrow1\text{ w}eek \\ the\text{ proportion is=}\frac{2.25\text{ km}}{1\text{ w}eek}=2.25\text{ kilometers per w}eek \\ \end{gathered}[/tex]Step 2
Let
x represents the number of weeks will take to repair the full stretch
then
[tex]\begin{gathered} 16\frac{1}{2}km\rightarrow x \\ 16.5\text{ km}\rightarrow x \\ \text{the proportion is=}\frac{16.5\text{ km}}{x} \end{gathered}[/tex]Step 3
as the proportions are the same
[tex]\begin{gathered} 2.25=\frac{16.5}{x} \\ \text{solve for x} \\ x=\frac{16.5}{2.25} \\ x=7.33 \end{gathered}[/tex]Hence, the answer is 7.33 weeks