You are preparing a performance review and have the following measurement at hand: pv = 300; ac = 200; and ev = 250. what is cpi of the project?
a) 0.80
b) 1.25
c) 1.50
d) 0.83

Respuesta :

CPI of the project is 1.25 so the correct answer is B

EV / AC is the formula used to calculate CPI. Here, 250 divided by 200 equals 1.25.The worth of the work that has been finished thus far in comparison to the budget is referred to as earned value.A. Schedule performance index equals (EV / PV) and schedule variance equals (EV - PV).The CPI is regarded as the most important EVM metric. It gauges the project work's cost effectiveness as of the measurement date.

To learn more about CPI:

https://brainly.com/question/26682248

#SPJ4

ACCESS MORE
EDU ACCESS
Universidad de Mexico