The net present value (NPV) method estimates how much a potential project will contribute to
-Select-
, and it is the best selection criterion. The
-Select-
the NPV, the more value the project adds; and added value means a
-Select-
stock price. In equation form, the NPV is defined as:


CFt is the expected cash flow at Time t, r is the project's risk-adjusted cost of capital, and N is its life, and cash outflows are treated as negative cash flows. The NPV calculation assumes that cash inflows can be reinvested at the project's risk-adjusted
-Select-
. When the firm is considering independent projects, if the project's NPV exceeds zero the firm should
-Select-
the project. When the firm is considering mutually exclusive projects, the firm should accept the project with the
-Select-
NPV.

Quantitative Problem: Bellinger Industries is considering two projects for inclusion in its capital budget, and you have been asked to do the analysis. Both projects' after-tax cash flows are shown on the time line below. Depreciation, salvage values, net operating working capital requirements, and tax effects are all included in these cash flows. Both projects have 4-year lives, and they have risk characteristics similar to the firm's average project. Bellinger's WACC is 8%.

0 1 2 3 4


Project A -900 620 395 200 250
Project B -900 220 330 350 700
What is Project A's NPV? Do not round intermediate calculations. Round your answer to the nearest cent.

$

What is Project B's NPV? Do not round intermediate calculations. Round your answer to the nearest cent.

$

If the projects were independent, which project(s) would be accepted?


-Select-

If the projects were mutually exclusive, which project(s) would be accepted?


-Select-

Respuesta :

This answer requires that we fill in the blanks

  • The net present value (NPV) method estimates how much a potential project will contribute to shareholder wealth
  • The larger the NPV,  the more value the project adds; and added value means a higher stock price.
  • The NPV calculation assumes that cash inflows can be reinvested at the project's risk-adjusted WACC
  • When the firm is considering independent projects, if the project's NPV exceeds zero the firm should accept the project.
  • When the firm is considering mutually exclusive projects, the firm should accept the project with the higher positive NPV.

What is the NPV?

In order to get the NPV we have to make the following calculations for the projects A and B.

This is calculated as

Project A

-900 + 620/1.08 + 395/1.08² + 200/1.08³ + 250/1.08⁴

= $355. 237

For the project B

We would have to perform similar calculation

Hence we would have

-900 + 620/1.08 + 395/1.08² + 200/1.08³ + 250/1.08⁴

= 378.98

From the calculations that we have done above, we can see that the value for project B is greater hence we have to choose project B.

Read more on NPV here:

https://brainly.com/question/17185385

#SPJ1