What is the missing amount in this physical flow of units? Work in process, August 1 9,000 tons Units started in August ? Units completed during August 19,000 Work in process, August 31 2,000 tons Group of answer choices 12,000 tons 10,000 tons 30,000 tons 8,000 tons None of these answers is correct.

Respuesta :

Based on the beginning and ending Work in Process and the units completed, the Units started in August must be 12,000 tons.

What amount of units were started in August?

This can be found by the formula:

= Units completed during August + Work in process Agust 31 - Work in process August 1

Solving gives:

= 19,000 + 2,000 - 9,000

= 21,000 - 9,000

= 12,000 tons

Find out more work in process at https://brainly.com/question/15299765.