When you engage in this action as a project manager, this is known as reforecasting.
The vendor in question is costing more than anticipated which means that there is an increase in spending. By shifting funds and recalibrating the budget, you are reforecasting.
In conclusion, option D is correct.
Find out more on budgeting at https://brainly.com/question/6663636.