The total number of parts is 1+3+5 = 9. The relevant fractions of the mix are ...
1/9 = portland cement
3/9 = 1/3 = sand
5/9 = crushed stone
Since the total is 765 ft^3, the ingredients required are ...
(1/9)(765 ft^3) = 85 ft^3 portland cement
(1/3)(765 ft^3) = 255 f^3 sand
(5/9)(765 ft^3) = 425 ft^3 crushed stone