A building contractor is to dig a foundation 45 feet long, 16 feet wide and 6 feet deep. The contractor pays 13 dollars per load for trucks to remove the dirt. Each truckload holds 4 cubic yards. How many cubic yards must be hauled away?

A building contractor is to dig a foundation 45 feet long 16 feet wide and 6 feet deep The contractor pays 13 dollars per load for trucks to remove the dirt Eac class=

Respuesta :

9514 1404 393

Answer:

  • 160 yd³ must be hauled
  • $520 is the cost

Step-by-step explanation:

There are 3 feet in a yard, so the volume of the hole is ...

  (45 ft)/(3 ft/yd) × (16 ft)/(3 ft/yd) × (6 ft)/(3 ft/yd)

  = (15 × 16/3 × 2) yd³ = 160 yd³ . . . volume to be hauled

__

The cost is $13/(4 yd³), so the total cost will be ...

  ($13/(4 yd³)) × 160 yd³ = $520 . . . cost of hauling