A building contractor is to dig a foundation 45 feet long, 16 feet wide and 6 feet deep. The contractor pays 13 dollars per load for trucks to remove the dirt. Each truckload holds 4 cubic yards. How many cubic yards must be hauled away?

9514 1404 393
Answer:
Step-by-step explanation:
There are 3 feet in a yard, so the volume of the hole is ...
(45 ft)/(3 ft/yd) × (16 ft)/(3 ft/yd) × (6 ft)/(3 ft/yd)
= (15 × 16/3 × 2) yd³ = 160 yd³ . . . volume to be hauled
__
The cost is $13/(4 yd³), so the total cost will be ...
($13/(4 yd³)) × 160 yd³ = $520 . . . cost of hauling