15 workers working 8hrs a day can complete a piece of work in 20 days. In how many days will 10 workers do it,working 6 hrs a day? please help!!

Respuesta :

ridmitharuka
ridmitharuka ridmitharuka
  • 02-08-2021

Answer:

40 days

Step-by-step explanation:

w1*h1*d1=w2*h2*d

15*8*20=10*6*d

2400=60d

d=2400/60

d=40

Answer Link

Otras preguntas

Scenario:bond's gym has developed a reputation for great customer service and low monthly membership fees. Due to this reputation, the gym has reached the maxim
If a 55-gallon drum represented all the water on Earth, how much water would be in the oceans? about 2 gallons about 53 gallons About 0.55 gallons
Witch of the following are other natural disasters that earthquakes produce
1 Chemical property of lanthanum
Sam works a part-time job making $11 per hour. This week, she worked for eight hours. Penni also worked this week. The money Sam earned is half as much as $30
Bethany had a beaker with a small amount of baking soda. She added a few drops of pickle juice to the baking soda and observed fizzing and bubbling. Based on he
what is the smallest size category of soil A. Sand B. Clay C. Gravel D. Silt APEX!!
why do archaeologist have to interpret evidence
what is [tex]27 \div378.00[/tex]
Find the rate of change for the situation. You run 7 miles in one hour and 14 miles in two hours.