Answer:
39.8
Explanation:
Calculation to determine Delivery cycle time
Using this formula
Delivery cycle time = Wait time + Throughput time = Wait time + (Process time + Inspection time + Move time + Queue time)
Let plug in the formula
Delivery cycle time= 29.7+ (0.4 + 0.3 + 3.8 + 7.4)
Delivery cycle time=29.7+11.9
Delivery cycle time=39.8
Therefore Delivery cycle time is 39.8