Answer:
1. Processing time:
Processing time = Theoretical time
Processing time is there for 6 minutes
Non processing time = Actual cycle time - processing time
= 7.35 - 6
= 1.35 minutes
2. Manufacturing Cycle Efficiency (MCE):
= Processing time / Actual cycle time
= 6 / 7.35
= 81.6%