Answer and Explanation:
The preparation of the schedule of cost of goods manufactured is presented below:
Direct material $232,500
Direct labor $65,500
Factory overhead $27,600
Total manufacturing Cost $325,600
Beginning work in process $158,200
Total cost of work in process $483,800
Ending work in process -$163,000
Cost of goods manufactured $320,800
In this way it should be prepared