Respuesta :

fichoh

Answer:

$94.24

Step-by-step explanation:

Given :

Diameter of circular slab = 18feet

Thickness of slab = 3 inches ; inches to ft = 3 /12 = 0.25 feets

Volume of slab = πd²t/4 = (π*18²*0.25) / 4 = 63.6 ft³

1 cubic yard = 27 feet

Volume in yard = 63.6 / 27 = 2.356 yd³

Concrete = $40 per yd³

Cost = $40 * 2.356 = $94.24