Answer:
10%
Explanation:
Demand (D) = 400 per day, Lead time (L) = 2 days, Container capacity (C) = 20, Kanban (K) = 44. Let X represent safety factor
K = D * LT * (1+X) / C
44 = 400 * 2 * (1+X) / 20
880 = 400 * 2 * (1+X)
1 + X = 880 / 800
1 + X = 1.1
X = 1.1 - 1
X = 0.1
X = 10%
So therefore, their current safety stock policy is 10%