Answer and Explanation:
The computation of the missing amount is as follows:
As we know that
The total manufacturing cost = Direct Materials Used + Direct Labor Used + Factory Overhead
So,
(1)
= $42,700 + $64,200 + $52500
= $159,400
(2)
= $298,000 - $78,100 - $144,000
= $75,900
(3)
= $314,000 - $57,400 - $113,000
= $143,600