Answer: Less than zero
Explanation:
Based on the information given, the NPV of the project will be calculated as the present value of cash flow earned minus the initial expenditure.
The present value of cash flow will be:
= 3/(1 + 15%)¹ + 3/(1 + 15%)² + 3/(1 + 15%)³
= 3/(1.15)1 + 3/(1.15)² + 3/(1.15)³
= 3/1.15 + 3/1.3225 + 3/1.520875
= 2.61 + 2.27 + 1.98
= $6.86 million
Then NPV will be:
= $6.86 million - $7 million
= -$1.14 million
Therefore, the correct option is "less than zero".