Mesa County contracts with New Construct Inc. to build a courthouse. New Construct hires Odell to excavate the site. Odell’s work damages adjacent properties. Mesa files a suit against the excavator, who argues that the county is not named in his contract with New Construct. Most likely, the court will hold that Odell is:_________

a. not liable because Mesa is not named in Odell’s contract.
b. liable on the ground that Mesa is an incidental third-party beneficiary.
c. liable on the ground that Mesa is an intended third-party beneficiary.
d. not liable because Odell’s contract was with New Construct, not Mesa.

Respuesta :

Answer:

c. liable on the ground that Mesa is an intended third-party beneficiary

Explanation:

             In a contract, the third-party beneficiary is a business or a person that benefits from the agreement and the terms of the contract that is made between the two other parties. According to law,  third-party beneficiary have certain rights which they can enforced if the contract is not fulfilled.

            In the context, Mesa is a third party beneficiary. The Mesa County enters into a contract with New Construct Inc. to construct a court house. Now New Construct Inc. again hires the firm Odell to excavate the land site.

            While excavating Odell damages few nearby properties, so Mesa County files a law suit against Odell. But Odell argues that Odell is not in agreement with Mesa County or have not entered into with any contract with the County, so Mesa cannot sue the excavator.

            But the court hold that as Mesa County is the third party beneficiary of the contract and have certain rights, Odell is held liable for the loss and should compensate for the loss to the County.