Answer:
12
Explanation:
The computation of the project completion time under the best-case scenario is shown below;
= Activity A1 weeks taken + activity A2 weeks taken
= 5 weeks + 7 weeks
= 12
We simply added the time taken by activity 1 and activity 2 so that the project completion time could come