Activity A1 takes 5 weeks, A2 takes 7 weeks, and A3 takes 4 weeks with a 50% probability and 10 weeks with a 50% probability. What is the project completion time under the best-case scenario, that is, A3 is early and takes 4 weeks

Respuesta :

Answer:

12

Explanation:

The computation of the project completion time under the best-case scenario is shown below;

= Activity A1 weeks taken + activity A2 weeks taken

= 5 weeks + 7 weeks

= 12

We simply added the time taken by activity 1 and activity 2 so that the project completion time could come

ACCESS MORE
EDU ACCESS