contestada

18. If an apprentice can do a piece of work in 24 days, and the apprentice and
instructor together can do it in 6 days, how long would it take the instructor to do
the work alone?
18. If an apprentice can do a piece of work in 24 days, and the apprentice and
instructor together can do it in 6 days, how long would it take the instructor to do
the work alone?

Respuesta :

Answer:

the number of days when instructor do the work alone is 8 days

Step-by-step explanation:

Given that

The apprentice can do the work in 24 days

And, the apprentice and  instructor together can do it in 6 days

We need to find out the number of days when instructor do the work alone

So,

[tex]= \frac{1}{6} - \frac{1}{24} \\\\= \frac{4 - 1}{24} \\\\= \frac{3}{24} \\\\= \frac{1}{8} \\\\= 8[/tex]

hence, the number of days when instructor do the work alone is 8 days