Answer:
A. 44 rolls at a time
B. 5.8 days
Explanation:
A. Calculation to determine How many rolls should Yellow Press order at a time
Using this formula
EOQ=√2*Annual demand*holding cost /Carrying cost
Let plug in the formula
EOQ=√2*2,750*$35/$625*16%
EOQ=√$192,500/100
EOQ=44 rolls at a time
Therefore How many rolls should Yellow Press order at a time is 44 rolls at a time
B. Calculation to determine time between orders
Time between orders=5.8 days