Answer:
Activity variance= $310 unfavorable
Explanation:
To calculate the activity variance, we need to use the standard costs and planned activity:
Activity variance= standard cost*planned activity - actual costs
Activity variance= (1,890 + 9*629) - 7,860
Activity variance= 7,551 - 7,860
Activity variance= $310 unfavorable