Answer:
If the part is purchased externally it will cost
$50,050 [$14.3 * 3,500]
If the part is made internally then the costs to be added up is:
Direct material per unit
Direct Labor per unit
Variable overheads per unit
and Fixed overhead per unit
the total of these costs per unit will be multiplied by the units required to be made i.e 3,500.
X Company should choose the option with the lowest total cost for 3,500 units
Explanation:
If the part is purchased externally it will cost
$50,050 [$14.3 * 3,500]
If the part is made internally then the costs to be added up is:
Direct material per unit
Direct Labor per unit
Variable overheads per unit
and Fixed overhead per unit
the total of these costs per unit will be multiplied by the units required to be made i.e 3,500.
X Company should choose the option with the lowest total cost for 3,500 units