The theoretical utilization of the ICU is:
= 0.25 or 25%
Explanation:
Inter-arrival time or flow rate of patients that arrive for service at the ICU = 4 hours
Mean length of stay = 6 hours
ICU's capacity to serve customers in 6 hours = 4*6 = 24 bed-hours
Total demand = 6 hours
Therefore, the theoretical utilization = flow rate of patients that arrive for service at the ICU in a given unit of time divided by ICU's capacity to serve customers in that same unit of time
= 6 hours/24 bed-hours
= 0.25