Answer:
b. $218.00
Explanation:
Calculation to determine the overhead rate for Department Y assuming the direct method is used
First step
Department Y$30,000
Maintenance Department $20,000
($60,000 × 150/450)
Personnel Department $4,500
($9,000 × 45/90)
Total $54,500
Now let calculate the overhead rate for Department Y
Department Y Overhead rate=$54,500/250
Department Y Overhead rate = $218
Therefore the overhead rate for Department Y assuming the direct method is used will be $218