Answer:
The capacity of this process in units per hour is:
= 2.43 tasks per worker hour.
Explanation:
a) Data and Calculations:
Number of tasks in the process = 9
Number of workers available = 3
Thus, each worker will accomplish 3 tasks (9/3)
Total time to accomplish the 9 tasks = Sum(80, 50, 30, 25, 55, 15, 45, 105, 40) = 445 seconds or 1.236 hours
Therefore, the capacity of the process per hour = 9/(1.236 * 3) = 9/3.708
= 2.43 tasks per worker hour