Answer:
$2575
Explanation:
Total variable overhead estimated=(6*31,500)= $189,000
Hence total overhead estimated=Total variable overhead estimated+Total fixed overhead estimated = $189,000 + $220,500 = $409,500
Hence, predetermined overhead rate = $409,500 / 31,500 = $13 per machine hour
Hence, total overhead applied=(13*400) = $520
Hence, total job cost=Direct material+Direct labor+Total overhead = $685 + $1,370 + $520 = $2575