contestada

Sheffield Corp. purchased land as a factory site for $1360000. Sheffield paid $116000 to tear down two buildings on the land. Salvage was sold for $8500. Legal fees of $5400 were paid for title investigation and making the purchase. Architect's fees were $46300. Title insurance cost $3900, and liability insurance during construction cost $4200. Excavation cost $15540. The contractor was paid $4500000. An assessment made by the city for pavement was $9500. Interest costs during construction were $252000. The cost of the land that should be recorded by Sheffield Corp. is $1486300. $1490900. $1476800. $1500400.

Respuesta :

Answer:

a. $1,486,300

Explanation:

Particulars                           Amount

Purchase cost                                $1,360,000

Cost to tear down two buildings  $116,000

Salvage                                         -$8,500

Legal fees                                      $5,400

Title insurance                               $3,900

Assessment cost                           $9,500

Cost of the land                            $1,486,300