15 men can finish a piece of work in 40 days. How many more men should be added so that the work will be finished in 30 days?​

Respuesta :

usmaninuwa367
usmaninuwa367 usmaninuwa367
  • 31-01-2021

Answer:

25 men will finish the work at 30 days

Answer Link
DWRead
DWRead DWRead
  • 31-01-2021
15 workers * 40 days = 600 worker-days
(600 worker-days)/30 days = 20 workers
Answer Link

Otras preguntas

Convert (20 possible points)
please help me with #15, it’s converting units
helppppp nowwwwww please
The ratio of adults and children attending a new exhibit one day at the museum was found to be 7:3 based on this ratio of 370 people attend that day how many w
How do I: Express 12a as the difference of two terms
Which legislative body has the power to try an impeached official
Could someone please help me?
What book in the bible does samuel l. Jackson quote in pulp fiction?
Answer each multiplication problem by using the difference or two ication problem by using the difference of two squares. Show your steps. 5) 73.67 6) 34.26 7)
Since viruses are typically 20-200 nm in diameter, the ____ microscope is best for viewing them.
ACCESS MORE