If 2 men and 3 boys can do a piece of work in 8 days, how long will 3 men and 4 boys take to do it?​

Respuesta :

LAASMITH7
LAASMITH7 LAASMITH7
  • 19-01-2021

Answer:

they would do it in 13 days

Answer Link

Otras preguntas

1) (-6,-7), (4,2) a) 13.5 b) 4.4 c) 1.7 d) 5.4
I’m confused can someone help me please
what is the answer to -3x = 4.2 ?
Plz help me with this plz pt.2
» What is Mary's running speed in miles per hour? 10/2 = ?
Read the passage, then answer the question that follows. As ever, sugar work was brutally hard. The workers woke early, and for the first few months they were “
Word that means that an organism does not move
Shaw Hagan was ordered to peel 200 potatoes. So far he has peeled 30% of the potatoes.How many more potatoes does Shaw still have to peel
We are going to redecorate our classroom. Our classroom____________________________
My company took in a total of $100,000 over the first quarter of 2021. This amount is called the - a Stock Price b Net Loss c Gross Revenue d Gross Profit