Answer:
Part 1
Calculation of activity-based overhead rates
Cost of Each Activity = Cost of Activity ÷ Number of times that Activity is performed
Loading and unloading = $97,000 ÷ 91,500
= $1.06 per piece
Travel = $467,000 ÷ 585,000
= $0.80 per mile
Logistics = $62,000 ÷ 3,150
= $19,68
Part 2
Overhead allocation to Job XZ3275
Loading and unloading (150 × $1.06) = $159.00
Travel ($0.80 × 200) = $160.00
Logistics ($19,68 × 0.75) = $14.76
Total Overheads = $333.76