Find project information, the diagram and table attached
Answer and Explanation:
Given the project information(attached) for the Air Control Company, we first draw our network diagram paying attention to the predecessors, example-activity A should come before every other activity .
In the table,
ES is early start time
EF is earliest finish time
LS is latest start time
LF is latest finish time
S is slack time
EF = ES + activity duration
LS = LF - duration
S= LF-EF
To calculate our critical path:
We follow all paths(add up their activity durations) from the network diagram down to the last activity
ABGH= 2+15+10+5
...
We select the path with the highest value which is:
ADFGH=2+13+15+10+5= 45