Answer:
when sea transportation is used:
safety stock = Z-score x √lead time x standard deviation of demand
- Z-score for 99% = 2.58
- lead time = 36 days
- standard deviation of demand = 4,000 units
safety stock = 2.58 x √36 x 4,000 units = 61,920 units
reorder point = lead time demand + safety stock
- lead time demand = 36 days x 5,000 units = 180,000 units
- safety stock = 61,920
reorder point = 180,000 units + 61,920 units = 241,920 units
when air transportation is used:
safety stock = Z-score x √lead time x standard deviation of demand
- Z-score for 99% = 2.58
- lead time = 4 days
- standard deviation of demand = 4,000 units
safety stock = 2.58 x √4 x 4,000 units = 20,640 units
reorder point = lead time demand + safety stock
- lead time demand = 4 days x 5,000 units = 20,000 units
- safety stock = 20,640
reorder point = 20,000 units + 20,640 units = 40,640 units