Answer:
b. $6,510.
Explanation:
The computation of the budgeted direct labor cost for July is shown below:
Budgeted Direct Labor cost is
= Direct Labor cost per hour × Number of hours
= 310 units × 1.5 hours × $14
= $6,510
hence, the correct option is b. $6,510
We simply applied the above formula and the same is to be considered
Therefore all other options are incorrect