The total overhead applied to Product P4 under activity-based costing is closest to: (Round your intermediate calculations to 2 decimal places.)

Respuesta :

Answer:

Total Overheads applied  = $482,494

Explanation:

Note: The full question is attached

Activity Cost Pool    Activity Driver    Expected Activity    Activity rate

Labor related              $110,800                 8400                    $13.19

Production orders      $52,260                 1200                      $43.55

Order size                   $817,390               6300                    $129.74

Total                             $980,450

Cost assigned to Product P4

Activity name          Activity Rates    Activity     Overhead Cost

Labor related                  $13.19             2800             $36,932

Production orders         $43.55            400              $17,420

Order size                       $129.74           3300            $428,142

Total Overheads applied                                            $482,494