Respuesta :
Answer:
7 days
Explanation:
Calculation for the early finish time of Task C
First step is to find the Early Start of task C
Using this formula
Early Start of task C = MAX (Early Finish of task A, Early Finish of task B)
Let plug in the formula
Early Start of task C= MAX(3,5)
Early Start of task C = 5
Now let calculate the Early Finish time of Task C
Using this formula
Earliest Finish = Earliest Start + Activity Duration
Let plug in the formula
Earliest Finish of task C = 5 + 2
Earliest Finish of task C = 7 days
Therefore the early finish time of Task C will be 7 days
The early finish time of task C is the sum of the early start time and the activity duration of the task. Hence, the early finish time of task C is 7 days.
Given the Parameters :
- Activity time of task C = 2 days
- Early finish, Task A = 3 days
- Early finish, Task B = 5 days
The early finish time of task C :
Early start time possible + Activity time of task C
Maximum value of the finish time of the preceeding task :
Early start time of task C = maximum(3, 5)
Early start time of task C = 5 days
Early finish time of C = 5 days + Activity time
Early finish time of task C = 5 days + 2 days = 7 days
Therefore, the early finish time of task C is 7 days