Probability Calculation: The critical path for a project was found to be 37 days. The variances total 27. What is probability of completing in 43 days

Respuesta :

fichoh
fichoh fichoh
  • 27-10-2020

Answer:

0.1241

Step-by-step explanation:

Given that:

Critical path = 37 days

Variance total = 27 days

Completion date (x) = 43 days

We obtain the Zscore :

Zscore = (x - critical path) / variance total

Zscore = (43 - 37) / √27

Zscore = 6 / √27

Zscore = 1.1547

Zscore = 1.155

Hence, probability of completing in 43 days :

P(Z > 43) = 1 - P(Z < 43)

P(Z < 43) = 0.8759

P(Z > 43) = 1 - 0.8759 = 0.1241

Answer Link

Otras preguntas

carlos y yo somos de canada a. somos canadieses b. eres canadiese c. son canadieses
Please Help Fast...?
Which of these phrases is an example of understatement?
name the glands associated with human digestive system​
During photosynthesis,
Healthcare costs are becoming an issue for many Americans. In just two years, the average family has seen an increase of 3 percent in insurance costs. The incre
identify the homophone pair that needs to be corrected in these sentences. If your going to the concert, may I ride in you're car too? their house is on the way
How can we make the world a better place, specifically towards discriminated people (LGBTQ+ Community, People of color, People with disabilities etc.) How can w
What is the difference between drug misuse and drug abuse?
Could someone help me with this question?